Power Engineering Consulting Joint Stock Company 2 (PECC2) – 300MW Thermal Power Plant Project
Client: Power Engineering Consulting Joint Stock Company 2 (PECC2)
Location: Kaleum District, Xekong Province
Duration: May 2023 – February 2024

Company Background:
Power Engineering Consulting Joint Stock Company 2 (PECC2) is a Vietnamese firm that plays a crucial role in energy infrastructure development, promoting economic growth, and ensuring energy security.

Services Provided:
ESL conducted the Impact Assessment for the project. The services included:

  • Inception Meeting:
    • Initial project briefing and discussions.
  • Desktop Review:
    • Review of existing project documents and information.
  • Initial Site Visit and Local Authority Discussions:
    • Site visit and initial consultations with local authorities.
  • Scoping Study and Terms of Reference:
    • Preparation of the Scoping Study report and defining the Terms of Reference.
  • Data Collection (Secondary and Field Surveys):
    • Collection of secondary data and field surveys for Environmental and Social Impact Assessment (ESIA) and Health Impact Assessment (HIA).
  • Data Analysis and Reporting:
    • Analyzing collected data and preparing reports.
  • Public Consultations:
    • Engaging with local communities and stakeholders through consultations.
  • Final Report Submission:
    • Submission of the final report to the client.