Xebangfai Run-off Riber Hydropower Project in Khammouane Province, located 30km from a Xebangfai crossing bridge, National Road No. 13S. The Project has an installed capacity of 15 MW and utilizes water from Nam Theun 2 to generate electricity.

 

In line with GOL regulation and Policy on Public involvement in an Initial Environmental Examination for Xebangfai Run-off River Hydropower Project, ESL in association with the Project Developer conducted a series of stakeholder consultations and meetings with Local Government Authorities and relevant sectorial offices as well as the respective village authorities. The last technical consultation meeting was held in May 2017 at DONRE office Khammouane Province, Lao PDR.